Let us first understand the importance of Network Diagram in project management as it is widely used across various industries including software, Mechanical, Aviation or even in Construction industry.
Now how to represent a project in form of diagram which we call it as โNetwork Diagramโ. How is it different from Gantt charts ? So Gantt charts only shows project schedules and focuses on tasks and time, while Network diagram in project management helps in defining the graphical relationship and sequence of tasks or activities to develop a project schedule. That is why network diagram offer broader scope to Project management.
What is Network Diagram ?
Network diagram usually shows a graphical association between different tasks and is used to develop a project schedule and determine ย the critical paths. Network diagram helps in determiningย the critical paths. w illustrating these activities either by using nodes or using arrows are the two different ways we can show relationships. So in this article are going to understand the difference betweenย Activity on Arrow (AOA)ย and Activity on Node (AON) what calculation we can do based on these networks to better plan our projects by project managers. Have you seen this post
Both these technique Activity on Arrow (AOA) and Activity on Node (AON) is a part of Program Evaluation and Review Technique (PERT). They are used to evaluate the time which is required complete the task especially if we talk about the complete project.
Lets first understand these terms independently.
Activity on Arrow (AOA)
It use arrows to represent activities while Activity on Arrow uses arrows to represent the activities while nodes stand for events.

It shows start to finish types of Relationship. Each node of Activity on Arrow contains three numerical values โ the Start Time, the Finish Time and the Float.
Start time : Earliest Start time or the time when activity actually starts.
Finish Time: Earliest finish time or the time when activity actually finishes.
Float: It basically tells how much extra time you have or the the amount of time a task can be delayed without resulting in an overall delay in completion of other tasks. It is calculated as Late Start time – Early Start time or Late Finish time – Early Finish time
Critical Path : is the longest path in terms of time required to complete activity from Start to Finish.
Event : in project management, itโs a specific point of time when something has actually started or finished.
Letโs see one example to help us understand this better.

Circles here represent the node, or the events and Activities are represented on the Arrows like A, B, C etc. ย So node #1 represent start of Activity โAโ and node #3 represent the End of Activity โAโ which become the start of Activity โCโ and Activity โDโ. This Activity โAโย will require some resources and time. Similarly, node #2 represent start of Activity โEโ and node #6 represent the End of Activity โEโ . Here the node #9 is the last node as we donโtย have any new which is Emanating or Starting. To understand how this numbering is done we first need to go through Fulkerson’s rule for numbering of nodes.
Predecessor and Successor activities
Here Activity โAโ must be completed before we can start Activity โCโ and Activity โDโ. In short Activity โCโ and Activity โDโ are dependent on Activity โAโ and we call Activity โAโ as predecessor for Activity โCโ and Activity โDโ or in other words Activity โCโ and Activity โDโ are successor activities to Activity โAโ.
Activity-on-Node (AON)
AON or Activity-on-node as the name signifies here the activity is placed on node.

It is also known as Precedence diagramming method. Unlike Activity on Arrow it shows start to start, Finish to Finish, Start to Finish, and Finish to Start types of relationship.
Letโs see one example to help us understand this better.

Circles or nodes represent the activities like Activity A, B, C etc. 1st node is always the START and Last node is the END node. Here Activity A and Activity B are starting at same time. Activity F cannot start until Activity E and Activity C both have been completed.
So the ultimate choice between Activity on Arrow and Activity on Node is purely a matter of personal choice.

Activity-on-Node
Interpretation
Activity-on-Arrow

Activity A comes before Activity B, which comes before Activity C


Activity A and Activity B must both be completed before Activity C can start


Activity B and Activity C cannot begin until Activity A is completed


Activity C and Activity D cannot begin until Activity A and Activity B have both been completed


Activity C cannot begin until both Activity A and Activity B are completed; Activity D cannot begin until Activity B is completed. A dummy activity is introduced in AOA


Activity B and Activity C cannot begin until Activity A is completed. Activity D cannot begin until both Activity B and Activity C are completed. A dummy activity is again introduced.

Watch this animated YouTube video for more details :
I hope this blog helped in understanding the basic concept in a simplified manner, watch out for more such stuff in the future.
๐ข๐ข ๐บ๐๐๐๐๐ ๐ด๐๐ ๐๐ ๐ณ๐๐๐:
Thanks!!!
For questions please leave them in the comment box below and Iโll do my best to get back to those in a timely fashion. And remember to subscribe to Digital eLearning YouTube channel to have our latest videos sent to you while you sleep.
โ๏ธ ๐๐ฒ๐ผ๐ฌ๐ต๐ช๐ฒ๐ถ๐ฎ๐ป: Copyright Disclaimer under section 107 of the Copyright Act of 1976, allowance is made for โfair useโ for purposes such as criticism, comment, news reporting, teaching, scholarship, education and research. Fair use is a use permitted by copyright statute that might otherwise be infringing. The information contained in this video is just for educational and informational purposes only and does not have any intention to mislead or violate Google and YouTube community guidelines or policy. I respect and follow all terms & conditions of Google & YouTube.

